Major parts of the nation’s capital are expected to experience power outages for almost two months.

The exercise, according to the Ghana Grid Company Limited, will commence from Tuesday, October 5 to December 5, 2021.

GRIDCo explains that the power outage has become necessary to assist it to execute some ‘planned works’ within the Achimota-Accra Central lines.

“The exercise has become crucial to transfer as much load as possible to Pokuase, Achimota, Accra East and Tema in order to limit loading at Mallam and Accra Central substations,” GRIDCo said in a letter requesting the Electricity Company of Ghana’s execution of the exercise.

THIS IS TRENDING:   Visionary Kwame Nkrumah Prophesied About Russia's Invasion Of Ukraine In His Book, ‘Dark Days In Ghana’

The said works, according to GRIDCo, will entail the decommissioning and replacement of the existing power transmission lines with high-capacity conductors.

Meanwhile, areas expected to be experienced power outages have been categorized into group A, B and C.

In group A, areas to be affected are Adabraka Old Timers, Mamprobi, Chorkor, Ageege, Lartebiokorshie, Valco Trust, Teachers Hall, among others.

For group B, includes Appolo Theatre, Asylum Down, Adabraka Market, Korle Gonno, Sukura, Mamprobi Poly Clinic, James Town, Mataheko etc.

THIS IS TRENDING:   COVID-19: Akufo-Addo Bans Post Funeral, Wedding Receptions

Areas in Group C will include Central Police Station, Cocobod, Kingsway, Abossey Okai, Chorkor, Appiah Danquah, Graphic Press House, SSNIT among others.

Check the time-table below;

We Will Love You To Join Our Over 160k Members Instagram Family With Just One Click @gharticles

Source: GhArticles.com

About Media President

Check Also

Ghana’s Cardinal Peter Turkson Among Top Contenders for Next Pope

Spread the love Following the death of Pope Francis, attention has turned to Ghanaian Cardinal …