Information gathered indicates that residents of Kasoa and its environs will experience 15 days of load-shedding and power outage.
The technical controller at the Millennium Development Authority (MiDA), William Amuna, noted that it forms part of planned activities to allow technicians to integrate a new power substation into the national grid.
READ ALSO: GES Out With New Reopening And Vacation Dates For SHSs
The temporary load-shedding exercise is scheduled to take place from May 27, 2021.
Amuna noted that work on the new power substation is expected to take 12 days but three more days will be required to monitor and fix any hitches that may arise.
He made this known when Energy Minister Mathew Opoku Prempeh visited the site of the ongoing project for the construction of a Bulk Supply Point (BSP) at Kasoa.
The Kasoa BSP is a 435 MWA capacity Gas Insulated Switchgear (GIS) substation, the second largest of its kind in the country.
It is being constructed to address low voltage and frequent power outage challenges caused by increasing domestic and industrial demand in Kasoa and its environs, including Senya Bereku, Bawjiase, and Nyanyanu.