Home / News / Pobiman Academy Project Is Progressing Very Well – Frank Nelson

Pobiman Academy Project Is Progressing Very Well – Frank Nelson

Hearts of Oak board member Frank Nelson says Pobiman Academy project is progressing very well following an inspection.

Mr Nelson, who is a member of the project committee, was at Pobiman was impressed with the works done so far by the contractors after his inspection on Thursday.

Profile photo, opens profile page on Twitter in a new tab

Phobians
@HeartsOfOakGH

Contractors excited with commitment from Hearts as the Project Committee members led by Mr. Frank Nelson visited Pobiman to assess the extent of work.

 

THIS IS TRENDING:   Former Capital Bank CEO Ato Essien Receives 15-Year Jail Term for Failing to Fulfill Repayment Agreement

Speaking to the media, he entreated the supporters to trust the leadership of the club as they are working hard to put smiles on their faces.

“We are appealing to our supporters to have trust in the board. The project is progressing very well”, he said.

Local construction firm, K.A Estates Company Limited commenced work on the project a few weeks ago and are expected to continue for 3 months.

After the 90 days, Turkish firm, Prefabex Construction will take over and use 7 months to complete what will be an ultramodern edifice.

THIS IS TRENDING:   Mahama’s Petition Is 7 Times More Serious And Sensible Than The 2012 Petition – Islamic Cleric Warns NPP

When completed the facility will have staff residence, senior housing unit, gym, training centres, laundry, swimming pool, lockers, toilet facilities, kitchen, as well as a dining hall.